CHARLESTON, WV (LOOTPRESS) – The Public Service Commission of West Virginia has approved plans for a $2.48 billion natural gas power plant in Monongalia County, along with three solar energy projects across the state.
The commission approved applications Tuesday, November 17, from Monongahela Power Company and The Potomac Edison Company to construct a 1,200-megawatt combined-cycle natural gas plant at the existing Fort Martin Power Station.
The companies also received approval to develop 70 megawatts of solar generation capacity at three locations: Valley Point near Albright, Davis near the Town of Davis, and Wylie Ridge in Weirton. The solar projects are expected to cost approximately $182 million.
The companies filed their application in February, citing a projected shortage of electric generation capacity beginning in 2029 and continuing through 2045.
As part of the approval, the commission authorized a surcharge allowing the companies to recover financing costs associated with the projects. The companies estimate the initial surcharge will increase residential electric bills by approximately $1.18 per month, or 0.9%.
The commission also directed the companies to provide annual updates on construction progress and costs beginning in January 2027. They must notify the commission at least 30 days before construction begins.
Additional information is available through the Public Service Commission’s website under Case No. 26-0108-E-CN.